I am working for the Air Liquide Global Engineering & Construction (Moscow, Russia) - https://www.airliquide.com/engineering-construction
During my work here I have changed several roles and worked in 2 Engineering Centers (most of the time in Moscow, in 2015 for 12 months in Frankfurt):
As Project Engineer:
FloxFill Moscow - station for filling cylinders (40 liters) and bundles (pack of 16 x 40l cylinders) with air gases and their mixtures:
- Management of technical studies between centers (France, Russia) and subcontractors
- Participation in development of Basic Design Documents in Project Team in Vitry, France (incl. Equipment list, Plot Layout, P&IDs, Electrical Consumer List)
- Preparation of input data for ITB for the design and bid analysis
- Management of Design Institute during preparation project documentation and detail design
- Review and verification of technical documentation developed by Contractors
- Support project documentation workflow to ensure its timely receipt, review as per Project schedule and its integration into Project Data Base
- Participation in construction and commissioning supervision on site for 5 months
FEED project - Methane-to-Methanol-to-Propylene Plant (during the assignment in Frankfurt am Main, Germany)
- Technical coordination with client, disciplines and vendors
- Support the interfaces between different disciplines
- Preparation of the Action items list during the Weekly Team Meetings and its follow-up
- Preparation of interdisciplinary documents (incl. Equipment Weights & Sizes list, list of applicable standards, Site Design Data) and procedures (Incl. Engineering Management Execution Plan, Freezing of key documents, Project Design Validation Plan)
- Assist QA/QC in different documents checks, KPI tracking and reporting, collecting of “Lessons Learned” items
- Preparation of Request for Quotation (RFQ) for Chemical Dosing Unit, follow-up of technical clarifications / negotiations with vendor
As Project Coordinator:
- Coordination (technical, financial and legal questions) between Customers (Russia) and Project Management Team (Champigny, France)
- participation in weekly progress reviews with the client
- Technical clarifications with Customer’s Design Subcontractor
- Clarification of shipping documents with Customer
- Preparation of documents for custom clearance
- Coordination of erection and commissioning intervention
- Preparation of contractual change-orders, certificates and invoices
Projects: 2 x N2 Generators,3 x O2 VSA Units
As Electrical Engineer:
• Responsible for electrical part of EPC projects for ASU (Air Separation Units): support projects at Design (Basic and Detail) and construction stages;
• Coordination between Customer, various E&C departments, external Design subcontractor, site works sub-contractors or AL supervisors related to electrical part
• Review and approval of detailed design drawings (electrical part)
• Preparation of technical RFQ specifications (scope of works and materials) to bid electrical site contractor, clarification with chosen Subcontractors;
• Preparation of RFQ specifications (0.4kV and 10kV Switchboards, 10 kV induction motors, transformers) and technical Bid analysis;
• Quality (as per ISO 9001) and technical audits at the manufacturer’s workshop, report preparation
• Solved problem caused by deviation between Russian and Western Standard Codes